Please use this identifier to cite or link to this item:
http://saruna.mnu.edu.mv/jspui/handle/123456789/4065
Title: | Environmental impact assessment for the Hulhumalé second phase reclamation & development of a harbour quay wall at Hulhumalé |
Authors: | Water Solutions |
Keywords: | policy, legal and administrative framework Project descriptions Methodology Existing environment Analysis of alternatives Stakeholder consultation and socio economic impact Environmental impacts Mitigation measures |
Issue Date: | Jan-2013 |
Citation: | Water Solutions. (2013). Environmental impact assessment for the Hulhumalé second phase reclamation & development of a harbour quay wall at Hulhumalé. Male': Maldives |
Abstract: | This report discusses the findings of a social and environmental impact study (EIA)
undertaken by Water Solutions Pvt. Ltd. at the request of Housing Development
Coorperation (HDC). This EIA report covers two projects; reclamation and coastal
protection of Hulhumalé phase 2 and development of a harbour quay wall at Hulhumalé.
The reclamation and coastal protection of Hulhumalé phase 2 is the first step to develop
Hulhumalé 2 in accordance with the Hulhumalé development master plan. This project
would reclaim 244 hectres of land at Hulhumalé lagoon and undertake coastal protection.
The two million cubic meters of the fill materials for the reclamation would be borrowed
using Trailing Suction Hopper Dredger from borrow sites identified by EPA. The harbour quay
wall project at Hulhumalé would be implemented on southern side by developing a 100 m
quay wall. A harbour basin would be dredged to -3 m at MSL and the excavated material
would be used as a back fill of the quay wall which will be constructed using concrete L
blocks.
Hulhumale development project was initiated by the government to address the issue
ofchronic congestion in Malé. The phase 1 of the project commenced in October 1997 and
the reclamation was completed in 2001. Under phase 1 of the project 188 ha was reclaimed
that would serve an estimated target population of 60,000. With the completion of existing
housing infrastructure, the land available for residential development is very limited. Hence
HDC is proposing to undertake the Hulhumalé second phase reclamation to facilitate the
development project needs be undertaken to meet the residential demand. The harbour quay
wall project is to facilitate a safe mooring area at Hulhumale for the vessels to load and
unload cargo.
Environmental and socioeconomic impacts of both components of the project were assessed.
The reclamation of the shallow lagoon, reef flat, creation of an entrance channel would have
irreversible impacts on the Hulhumalé reef. The impacts of the project result mainly from
dredging and reclamation work. The impact of both activities would be of sedimentation.
This impact is considered to be minor and short-term. During dredging and reclamation
activity, impact of sedimentation on inhabited islands, resorts and diving sites are a concern
that needs to address. The reclamation and coastal protection of Hulhumaé phase 2 and
harbour quay wall project would have socio-economic benefits to the greater Malé region.
The socio-economic benefit outweigh the negative impacts of the project on the physical
environment of the Hulhumalé especially allowing more land to further expand the urban
centre development of Hulhumalé.
Mitigation measures for these anticipated impacts have been identified and outlined in
detail, including sedimentation and stagnation control methods and measures for minimizing
negative effects of generation of waste. These mitigation measures will have to be followed
in order to minimize environmental damage. The details of the project have been established
based on the Hulhumalé master plan. Alternative locations and alternative designs have been investigated for the different
components of the project. However, the present project design seems to be feasible option
in terms of costs, durability and safety.
An environmental management plan with environmental monitoring has been developed
including the most important elements that require regular checks. This monitoring
component need to adhered to and would allow to assess the changes due to the reclamation
of additional land at Hulhumalé lagoon.
Although the project involves inevitable negative environmental impacts, such impacts are
predicted to be not severe as to not undertake the project in accordance with the master plan.
The project is justifiable in light of the socio-economic conditions and anticipated benefits
resulting from the project, which seem to outweigh the negative environmental impacts. |
URI: | http://saruna.mnu.edu.mv/jspui/handle/123456789/4065 |
Appears in Collections: | ތިމާވެށި Environment A
|
Items in Saruna are protected by copyright, with all rights reserved, unless otherwise indicated.