Environment - ތިމާވެށި

Browse

Search Results

Now showing 1 - 10 of 34
  • Thumbnail Image
    Item
    Technical Report
    Environmental impact assessment for harbor extension works at Fares-Maathodaa, Gdh. Atoll
    (2016-04) Land and Marine Environmental Resources Group
    Background The non-technical summary outlines the findings of the Environmental Impact Assessment of the proposed harbour extension works at Fares-Maathodaa, Gaafu Dhaalu Atoll. The proponent of the proposed project is Ministry of Housing and Infrastructure. The total estimated cost of this project is USD 843,060. The proposed project involves extension of the existing facility (which lies on the northern side of the island) by addition of 61m (along its length) to the eastern side of the facility. The project also involves construction of the main quay wall along the extension area and a sand bund breakwater along the outer boundary. Dredged material sourced will be disposed along the shoreline to the east of extension area. Key impacts, mitigation measures and alternatives Impacts on the environment have been considered for the constructional phase and post constructional phase of the project. These impacts have been identified through interviews with the project management team, field data collection and surveys and are also based on past experience of consultant in similar development projects. Impact analysis was done using the Leopold matrix. The impacts identified are described according to their location, probability of impact, magnitude, significance and duration. Mitigation measures have also been identified for impacts which are irreversible in nature. Impact analysis showed that the main impact due to the project was during the construction phase, due to dredging activity. This impact was also anticipated to be of low effect due to the location (shallow intertidal area with seagrass beds) and scale of project (even though loss of seagrass beds from project site is a permanent impact). Overall, impacts identified were found to be of low effect and restricted to the project site, with temporary effects. Positive impact due to the project is the availability of a bigger and more planned area (dedicated area for unloading and passenger use) for use by the numerous vessels of the island and those who visit the island. Mitigation measures are discussed in the report for potential impacts, such as limiting dredging activity to low tide phase to reduce possible sedimentation impacts. Detailed mitigation measures are discussed in Section 11 of the report. Given the scope of the project and need alternative has only been considered for the material to be used for breakwater construction and location of extension. The no-project scenario which was also considered, is not feasible, given the scope of project and associated impacts on environment which are which are mainly of low effect and short term. The benefits on continuation of project outweigh the impacts and hence the no-project scenario is not considered a feasible option. The Consultant feels that the project is feasible with proper implementation of the mitigation measures proposed to minimize the impact on the environment. Stakeholder Consultation Stakeholder consultation was undertaken with Island Council regarding the concept drawing formulated by MHI. The council stated that they require a side quay wall to be included in the eastern side and if excess dredged material is available back filling areas where erosion is observed. Based on the stakeholder consultation, MHI agreed to change the concept design to include a side quay wall at the eastern side. The revised final drawing is provided in Appendix 5 of this report.
  • Thumbnail Image
    Item
    Technical Report
    Environmental impact assessment report for construction of 14 storey mix use building at STELCO compound, Male’
    (2016-11) Land and Marine Environmental Resources Group
    1.1 Background This report is an Environmental Impact Assessment (EIA) for the development of a 14 storey mix use building at State Electric Company Limited (STELCO) compound. The proponent of the proposed project is State Electric Company Limited (STELCO). 1.2 Project Detail The proposed project involves development of a mix use building in the compound of the current STELCO plot, right next to the current STELCO head office building in Male‟. The basement level and part of the ground level is dedicated to parking while the remaining area of the ground floor is allocated for the lobby, circulation and showroom. The first floor of the building is allocated for shops and the second and third floors are to be used as office spaces. The fourth and fifth floor are dedicated for use as convention halls and floors six to ten are to be used as offices. The floors eleven and twelve are allocated for residential apartments while the thirteenth floor has recreational areas such as aerobics/saloons/pool bar/café/pool and gymnasium. Finally, the fourteenth floor which is the terrace has a space allocated for the green roof while the lower roof has tanks for rainwater collection. As part of the construction works, ground improvement measures will be undertaken through micropiling work. 1.3 Key impacts, mitigation measures and alternatives 1.3.1 Key impacts Impacts on the environment from various activities of the project have been identified through interviews with the proponent, field data collection and surveys as well as based on past experience in similar construction projects. In any development project major direct impacts to the environment (either short-term or long-term) occur mainly during the construction phase. Potential direct or indirect impacts which are anticipated to arise due to the proposed works are as outlined below:  Ground water contamination/salinisation due to dewatering works. This is foreseen to be minor and short termed.  Social impacts due to groundwater shortage: impact is foreseen to be minor and short termed  Noise and air pollution during the construction works due to machinery and equipment; impact intensity will vary during different phases of the project  Vibration impacts during micropiling work  Impact on traffic due to road closure during foundation and floor slab casting periods: minor to moderate impact which is short termed and only during a few days of the project Operational phase of the project is not envisaged to have significant negative impacts. 1.3.2 Mitigation measures There are a number of actions that can be taken to minimize the identified impacts. Mitigation measures are selected to reduce or eliminate the severity of any predicted adverse environmental effects and improve the overall social and environmental performance of the project. Mitigation measures are mainly discussed for the construction stage since no significant operational impacts are envisaged in such projects apart from maintenance works. During the construction stage it is important to take measures to minimize dust spread, assess adjacent building condition during dewatering, excavation and micropiling works and monitor groundwater shortages. Dewatering should also be carried out as per outlined in the Dewatering Regulation which has been gazetted on 31st December 2013 and will come into effect from January 31st 2014. Detailed mitigation measures are outlined in Table 21 of the report. The report also highlights Grievance redress mechanisms in Section 10.1 of the report. While the operational stage is not envisaged to have significant negative impacts, it should be noted that the proponent has already identified certain measures to conserve energy, and minimize the impact on the environment due to various operational activities. These measures are identified in Section 5.10 of the report. 1.3.3 Alternatives Given the scope of the project and the utilization of typical construction methodology and foundation types, alternatives have only been considered for very few components including:  the method used for soil stabilization  discharge location of extracted ground water Additionally, a „no-project‟ scenario has also been considered, but not considered feasible due to the need for the project (increased office space and convention halls). Hence given that the impacts to the environment due to the project are mostly minor impacts, this option has been considered not feasible. Alternatives are discussed in Section 9 of the report. The Consultant concludes that the proposed project and methods identified are feasible and can be carried out with minimal impact on environment, especially through implementation of mitigtion measures identified in the report.
  • Thumbnail Image
    Item
    Technical Report
    Environment impact assessment for the construction of weather mast at Hoarafushi, HA. Atoll
    (2016-03) Land and Marine Environmental Resources Group
    The non-technical summary outlines the findings of the Environmental Impact Assessment of the construction of a 77m (with the instrument boom and lightning arrester total hight will be 82m) high weather mast at HA. Hoarafushi for collection of wind data. The proponent of the proposed project is Ministry of Environment and Energy. The total estimated cost of this project is USO 191,000.00. . This project is a component of "Renewable Energy Resource Mapping and Geo-spatial Resource Mapping - Maldives Project". The current works are part of second phase of the project which involves data collection for 24 months at several locations around Maldives for developing a validated mesoscale wind atlas for the Maldives. Key impacts, mitigation measures and alternatives The proposed project is not expected to have any impacts during the operational phase. The Impacts on the environment from various activities of the construction work have been identified through interviews with the project management team, field data collection and surveys and are also based on past experience of consultant. Mitigation measures have also been identified for impacts. Impact analysis was done using the Leopold matrix. Impact analysis showed that impact due to the project was minor and on various parameters of the terrestrial environment such as vegetation and groundwater. Mitigation measures are discussed in the report for potential impacts. Given the scope of the project the only possible alternatives for the project was a no-project scenario or alternative location for construction of tower. The "do-nothing" option or no project scenario would mean that the data requirement for the wind model will not be available and alternative island to be selected. The selection of the island is made based on phase one of the project which identified locations for data points spread around the island for modeling purposes. Since renewable energy ventures and development of the sector is a policy of government it is essential to undertake all data collection and feasibility studies to be able to make an informed decision. Furthermore the project is a grant from World Bank and government is required to fulfill its obligation in facilitating the project. Therefore given that the benefits of project are high and environmental impacts are low, the no project scenario is rejected.
  • Thumbnail Image
    Item
    Technical Report
    Environmental impact assessment for construction and development of water supply system at Dhangethi, Adh. Atoll
    (2016-12) Land and Marine Environmental Resources Group
    The non-technical summary outlines the findings of the Environmental Impact Assessment of the construction and development of a freshwater production and distribution system at ADh. Dhangethi. The proponent of this project is the Ministry of Environment and Energy and total estimated cost of the project is MRF 17 million. To meet the water supply demand and to provide a quality treated water RO desalination with rainwater collection scheme is proposed for the island. The project involves the setup of a RO plant facility with two RO plants each with a capacity of producing 60m3 of freshwater per day One RO plant will be operational at anyone time while the remaining plant will be kept as a backup. Rainwater will be collected from the public buildings which will go through separate treatments before being mixed with RO desalinated water. Key impacts, mitigation measures and alternatives Impacts on the environment from various activities of the project development work (constructional impacts) and operational impacts have been identified through interviews with the Project management team, field data collection and surveys and are also based on past experience of consultant in similar projects. Impacts were analysed for their significance with the aid of a Leopold Matrix. In any development project, major direct impacts to the environment occur mainly during the construction phase. Potential direct or indirect impacts on the environment from the proposed project include:  Minor to moderate impacts to the groundwater resource during drilling and construction work  Impact on vegetation due to the need to cut down vegetation located at the plot  Impact due to air and noise pollution during construction work  Impact on marine environment due to discharge of brine  Positive impact on social wellbeing and health Mitigation measures are discussed for the activities which would have potential impacts during the construction and operational phase of the project. In general, during the construction stage it is important to use a method of construction which has the least impact on the environment. Specific measures highlighted include following of established guidelines when carrying out excavation works and dewatering and transplantation of Coconut palms around the periphery of the project site. Detailed mitigation measures are discussed in Section 11 of the report. Alternatives have been considered for various components of the project and are given as possible options that may be either more practical or less expensive to the preferred options. The proposed alternatives also have taken into consideration the environmental consequences resulting from these options as compared to the preferred options. The following components of the project have been discussed in providing these alternatives;  Location of RO plant facility  Source of feedwater for RO plant  Brine discharge location The no-project scenario is also considered, which would mean that all environmental impacts due to the project would no longer be an issue. However, this also means that the community would have to continue using only rainwater and groundwater as main freshwater sources. Additionally, it would also mean increased health risks faced by the community due to the use of contaminated water and the loss of potential additional job creation during the operation of the service. The environmental impacts predicted for the project are minor to moderate, hence the benefits of establishing the system, though with a cost to the environment is seen to be far more beneficial than the cancellation of the project, as the health risks faced by the community is not something that should and can be overlooked. Therefore the “no-project” scenario is not a feasible solution and it is recommended that the project be continued, but with the proper implementation of all mitigation measures proposed in the report. Details of the various alternatives considered and the selected alternatives are shown in Section 10 of the report.
  • Thumbnail Image
    Item
    Technical Report
    Environmental impact assessment for the development of aquatic animal quarantine facility at Ibrahim Nasir International Airport
    (2016-07) Land and Marine Environmental Resources Group
    The non-technical summary outlines the findings of the Environmental Impact Assessment of the proposed construction of a live aquatic animal quarantine facility at the Ibrahim Nasir International Airport. The proponent of the project is the Ministry of Fisheries and Agriculture. The proposed project is a part of the institutional strengthening component of the Mariculture Enterprise Development Project (MEDeP) implemented by the Ministry. It involves construction and set up of the live aquatic animal quarantine facility, which is inclusive of a quarantine building and pump station. The seawater for the holding tanks will be sourced through a seawater well located at the lagoon area to the west of project site (back reef area of Hulhule reef), while wastewater discharge will be through pipeline laid from facility to the western reef (pipeline south of facility and run near quay wall of harbor southern side of Hulhule Island Hotel, close to the along-side berthing area for fuel tanker ships). Key impacts, mitigation measures and alternatives Impacts on the environment from various activities of the construction work and during the operation of the facility have been identified through interviews with the project management team, field data collection and surveys. The impacts identified are also described according to their location, extent and characteristics. Impact analysis was done using the Leopold matrix. Impacts due to project were few and minimal, mainly with low effects. Impacts were mainly envisaged on seawater quality and marine environment, as well as vegetation (due to removal of coconut palms). Details of impact analysis are discussed in Section 9 of the report. Detailed mitigation measures are discussed in Section 11 of the report. Given the minimal impacts, mitigation measures due to project are few. However, the formulation of contingency plans in case of equipment breakdown or incidence of other events such as fire and floods should be given a priority. Due to the scope of the project and the means of implementation, an alternative scenario has also been given for the means of wastewater disposal. The „no project‟ alternative is also considered. Although this would mean avoidance of environmental impacts, this option is not feasible due to the necessity of the project, especially if the mariculture sector was to expand. Hence the project, with current designs and methods is considered feasible, and Consultant feels that appropriate mitigation measures have been given in the report.
  • Thumbnail Image
    Item
    Technical Report
    Environmental impact assessment for backfilling of lake area and reconstruction of boundary wall at Funadhoo, Kaafu Atoll
    (2016-05) Land and Marine Environmental Resources Group
    The non-technical summary outlines findings of the Environmental Impact Assessment of the backfilling of Lake area/water body and reconstruction of boundary wall at K. Funadhoo. The proponent of the proposed project is State Trading Organization Plc. The total estimated cost of this project is USD 200,000.Due to the scope of the project, impacts on the environment have only been considered for the constructional phase of the project. These impacts have been identified through interviews with the project management team, field data collection and surveys and are also based on past experience of consultant in similar development projects. The impacts identified are described according to their location, extent and characteristics. Mitigation measures have also been identified for impacts which are irreversible in nature. Impact analysis was done using the Leopold matrix. Since majority of the work for the backfilling of Lake area had already been completed prior to consultation with the EIA consultant, any further impacts were mostly insignificant. Terrestrial vegetation was identified as the most sensitive component of this project. Moreover, impact analysis showed that most of the proposed works are anticipated to have positive outcomes. Mitigation measures are discussed in the report for potential impacts, including the following: 􀁸 Relocation of mature plants which are not too deeply rooted 􀁸 All machinery used should be well maintained and relevant staff well trained to avoid accidental spillage during construction phase Detailed mitigation measures are discussed in Section 11 of the report. Given the scope of the project, alternative has only been considered for the technique used for the bracing pipe/rod connection. The no-project scenario which was also considered is not feasible, given the scope of project and associated impacts on environment which are minor. Hence the project is considered feasible with proper implementation of the mitigation measures proposed to minimize the impacts on the environment.
  • Thumbnail Image
    Item
    Technical Report
    Environmental impact assessment for coastal modification and construction of a causeway between Hoan’dehdhoo and Madaveli, Gaafu Dhaalu Atoll
    (2016-10) Land and Marine Environmental Resources Group
    The non-technical summary outlines the findings of the Environmental Impact Assessment for the construction of a causeway of length 441m, linking Hoan‟dehdhoo and Madaveli and the reclamation of 3.5ha of land area in Madaveli in Gaafu Dhaalu Atoll in the South of Maldives. This project was earlier addressed through another EIA submitted in 2012 (SEAMARC, 2012), though due to delays in implementation of the project, the EIA period is now void. Furthermore, design of the causeway and changes to other components of the project, requires submission of a second EIA for the project, prior to commencement. The project proponent of the proposed project for coastal modification and construction of causeway between Hoan‟dehdhoo and Madaveli is Ministry of Housing and Infrastructure while the contractor for the project is Maldives Transport and Contracting Company Plc.The project includes two components: 1. Construction of a causeway linking the islands of Hoan‟dehdhoo and Madaveli. The proposed causeway has a total length of 441m and width of 15m. The causeway between the two islands will be constructed in two parts connected by the uninhabited island of Haadhoo which lies in the shallow lagoon area between the two islands. Construction of the causeway will be through reclamation of land area between the islands, whereby stretch of land between Madaveli to Haadhoo is proposed to have a length of 261m, while that between Haadhoo and Hoan‟dehdhoo is proposed to have a length of 180m. The area will be reclaimed to a height of 1.4m above Mean Sea Level (MSL) and protected through construction of a sand cement bag revetment along the whole length of both sides of the causeway. Concrete culverts at 50m apart will be placed along the length of the causeway to allow tide flow. The length of the culverts is equal to the width of the causeway (15m) and 6m wide. 2. The second component of the project is the reclamation of 3.5ha of land at the southeastern side of Madaveli. Reclamation of the land will be to a height of 1.3m above MSL, using sand sourced from the lagoon area. Proposed borrow area for the project is located at the eastern side lagoon between the two islands. A total of 73,500m3 of sand is required for this work and the recommended borrow area is proposed to be dredged to a depth of -3m from the seabed.Impacts on the environment from various activities of the project (both during construction and operation) have been identified through interviews with the project management team, field data collection and surveys and are also based on past experience of consultant in similar development projects. Impacts which have been identified were analysed with the aid of a Leopold Matrix, which gives numerical assessment of the magnitude and importance of an impact. The proposed project involves construction of a causeway between Madaveli and Hoan‟dehdhoo and reclamation of 3.5ha of land area on the southeastern side of Madaveli. The main construction stage impact associated with the project is due to dredging and reclamation works, which have the potential to greatly impact the marine environment through direct habitat loss and indirectly through sedimentation. Impacts discussed are;  Direct loss of habitat due to dredging and reclamation work  Sedimentation impact due to dredging and reclamation work  Mobilization of equipment and labor  Impact on vegetation due to causeway and road construction  Noise, vibration and disturbance to nearby residents  Impact on vegetation  Pollution of natural environment due to possible spillage, solid waste, disposal of untreated waste water  Risk of accidents and pollution on workers and local population The proposed borrow area is located at the eastern side of the reef between the two islands. Dredging works is proposed to be undertaken using excavator and transported using interim bonds. Dredging works at the borrow area will create sediment plume and expected to flow eastwards (tidal currents). Sand bund is proposed around the periphery of dredging area hence spread of fines will be reduced. The causeway construction works will close the aperture between Madaveli/Haadhoo/Hoan‟dehdhoo and stop flow of water. The culverts will be laid after connecting the islands, hence sediment plume will be minor and only depend on tidal currents (west to east on the eastern side of causeway). Impacts of sedimentation during causeway reclamation are therefore categorized as moderate and short termed. Significant negative impact on western side (southern side bay area of both islands) shoreline and immediate land area adjacent to proposed causeway is envisaged in the operational phase. In the event of storm surge (udha), water will pile up at the western side bay area causing rise of water level consequently causing flooding. Even at present, periodic flooding is experienced during SW monsoon due to storm surge. Therefore protection against storm surge is thought to be less and negative impacts high due to current design of the causeway. Mitigation measures for the various components which are expected to have impacts, have been proposed in the report, including the recommendation to revise the current design of causeway and include revetment at the southern side of reclamation area. Given that this project is developed specifically for these two islands, an alternative location is not considered. Alternatives for the project have been considered for the following;  Design of the causeway  Materials used to construct the revetment  Borrow location  Reclamation design The no-project scenario is also considered, the environmental impacts which arise due to the project such as change to hydrodynamics and loss of marine habitat and possible increase in surge related flooding can be avoided. However, should this option be chosen, this means that the social benefits (increased employment opportunities, easier travel between islands, better public services and increased housing plots) provided by the project will be cancelled. Hence given the high positive impact on the socioeconomic environment, discontinuation of the project is not seen to be a feasible option. Although this may be the case, the current causeway design is envisaged to increase surge related flooding hence this component is not feasible and needs to be revised. Details of the various alternatives considered and the selected alternatives are shown in Section 10 of the report. The consultant concludes that the proposed project component, especially the causeway with current design which lacks coastal protection measures in the vicinity of the causeway on either island is likely to cause significant environmental damage (specifically coastal flooding) at both islands. It is therefore recommended that an alternative design for the causeway should be considered.
  • Thumbnail Image
    Item
    Technical Report
    Addendum 2 to the environmental impact assessment report for the development of a transit hotel and luxury villas at Baa Finolhas
    (2014-11) Land and Marine Environmental Resources Group
    This non-technical summary highlights the findings of the Second Addendum to the Environmental Impact Assessment of the proposed development of a Transit Hotel and Luxury Villas on the island of Finolhas in Baa Atoll by Coastline Hotels and Resorts Pvt Ltd. The proponent has brought changes to the concept plan, based on which the EIA for the project was approved. The EIA report was submitted and approved on 21st January 2013. A revised concept plan has been approved and a conditional development approval by the Ministry of Tourism has been provided, conditional to environmental clearance by EPA. This addendum therefore covers description of these changes, their environmental impacts and any mitigation measures that are required in context of environmental impacts and mitigation measures described in the EIA of 2013, The changes proposed to the concept are;  Quay wall construction on the land side of the harbour basin  Revetment construction on the south western shoreline  Construction of a temporary jetty on north eastern lagoon These changes are fully discussed in Section 4 of the report, while impacts and monitoring required are discussed in Sections 5 and 6. While the proposed changes to the concept range from minor to moderate (few cases), the environmental footprint of the proposed changes are anticipated as low. Revetment works proposed is likely to have a positive impact to the shoreline where it has been proposed and nearby shoreline, as the primary objective of the revetment was to control severe erosion in this area. Quay wall, although not part of original concept would provide additional mooring space within the harbour in addition to reducing sediment fill up into the harbour basin without the quay wall. The quay wall construction will not completely block water flow across the harbour along the shoreline as there are gaps in the revetment beneath harbour wall ways. Temporary jetty has been proposed for the construction period only (second phase of the overall project, described in EIA 2013). Hence no significant additional impacts are expected to occur due to the changes to the concept plan and construction of temporary jetty. Therefore, it is concluded that the mitigation and monitoring proposed in the EIA for this development is more than sufficient to address these requirements of the project.
  • Thumbnail Image
    Item
    Technical Report
    Environment impact assessment for flood mitigation and reclamation works at Fares-Maathoda, Gdh Atoll
    (2013-02) Land and Marine Environmental Resources Group
    The non-technical summary outlines the findings of the Environmental Impact Assessment for the development of flood mitigation measures at Fares-Maathodaa in Gaafu Dhaalu Atoll in the South of Maldives. The island is susceptible to flooding due to storm surges and powerful swells and was one of the worst affected islands during the powerful swells which hit the Maldives in 2007, with the entire island of Fares and one third of Maathodaa being flooded. Hence the need for proper flood mitigation measures is crucial in order to ensure the safety of the community of the island during possible similar events which may occur in the future. The project proponent of this project is United Nations Office for Project Services, who were requested by United Nations Development Programme to provide support of developing a comprehensive coastal protection and drainage management support approach to the southern island of Fares-Maathodaa. This project is part of a climate change package from the Danish Government of about $10 million to UNDP. The bid for the provision of consultancy services for carrying out detailed designs for flood mitigating measures at Fares-Maathodaa Island was won by Lanka Hydraulic Institute Ltd (LHI) (and their local counterpart, Riyan Pvt Ltd) and UNI Consulting Services. After conducting a study at the site and undertaking numerical modeling of five engineering interventions which were then proposed to UNOPS and the Government of Maldives it has been decided to construct a continuous offshore breakwater structure of length 734 m, joining the headlands of Fares and Maathodaa on the southwestern side of the island. Physical modeling was then conducted on this option. The breakwater would be constructed using armour rocks of varying sizes and weights which have been chosen based on their ability to resist extreme wave conditions without significant displacement. The core of the breakwater will be filled with dredge material obtained from within the enclosed lagoon area. The project also involves the reclamation of the enclosed lagoon area of 191,700 m2, though this component will be carried out as a second phase of the project, within a short duration of completion of the breakwater construction. Details of this phase will be addressed in a separate report formulated prior to commencement of this project. The construction of the breakwater will be undertaken by UNOPS, while reclamation will be funded and undertaken by the Government of Maldives.
  • Thumbnail Image
    Item
    Technical Report
    Environmental impact assessment : wharf reconstruction and upgrading of the existing berthing facility and slipway at FSM Thilafushi plot
    (2013-03) Land and Marine Environmental Resources Group
    The slipway and berthing facility used by Fuel Supplies Maldives Pvt Ltd on Thilafushi is located on the northeastern side of the island. The facility has undergone extensive damage over the years and is also not sufficient to fully cater to the needs of the company. The proposed project involves the repair of the existing slipway and modification of seaward wharf of the plot. The seaward wharf will be extended by 311 and protected by sheet piles. The wharf will be designed to cater to vessels of 2000 tonnes (alongside berthing facility). The Slipway will be designed to cater for vessels of 200 tonnes. The project also involves reconstruction of the plot separating the wall from adjacent plot at the eastern side. The proponent of the proposed project is Fuel Supplies Maldives Pvt Ltd (FSM). Fuel Supplies Maldives, incorporated on 18th December 2000 is now a joint venture between State Trading Organisation (STO) and the Maldives National Oil Company (MNOC) formed with the main objective of streamlining fuel distribution in the country and to offer easy and convenient access to fuel throughout the country (FSM website, accessed March 2013). The total estimated cost of this project is ME 1.5 million. This document presents the findings of an Environmental Impact Assessment (HA) for the repair of the existing slipway and modification of seaward wharf of the plot used by ESM Pvt Ltd in Thilafushi. Developers of such development projects are required to carry out EIA. studies under the Environmental Act of Maldives. The developer is required to obtain approval of the Environmental Protection Agency (EPA), prior to the implementations of any development activities on the island. Land and Marine Environmental Resources Group Pvt Ltd have been engaged by FSM Pvt Ltd to prepare the EIA and to provide assistance in other environmental related activities. This HA is prepared in accordance with Environmental Impact Assessment Regulations 2012 and the environmental policy and guidelines of the Government of Maldives.