Please use this identifier to cite or link to this item: http://saruna.mnu.edu.mv/jspui/handle/123456789/5018
Title: First addendum : environmental impact assessment to Guraidhoo harbor construction project, Kaafu Atoll, Maldives
Authors: ހުސެއިން ފިރުދޯސް
Hussain, Firdous
Issue Date: 14-Jun-2016
Publisher: Hussain، F. (2016). First addendum : environmental impact assessment to Guraidhoo harbor construction project, Kaafu Atoll, Maldives. Male': Maldives
Abstract: This is the first Addendum to the EIA for the harbour project being undertaken in Guraidhoo, Kaafu Atoll. The project is proposed by Ministry of Housing and Infrastructure. An environmental assessment was undertaken for this project in March 2014. According to the EIA, justification for the project is to provide safe and secure harbouring facilities to the vessels, especially the larger ones. The island only had a natural harbour with some jetties without a breakwater for providing protection during the rough weather conditions. As a result government proposed a harbour construction project in K.Guraidhoo. K.Guraidho Harbour Construction project was initially begun under the project, “Design and Build of Harbours in 10 Islands” in 2014. The agreement was signed on 9th February 2014 and harbour construction work begun in 25th February 2014. Project work lasted till 30th October 2014 during which period, Quay wall construction and dredging was completed. However, due to quota restrictions and other reasons, during the years 2013 and 2014, Maldives has undergone a difficult time in sourcing rock boulders for construction projects in the country. As a result, K.Guraidhoo harbor construction site was temporarily demobilized on 30th October 2014 for using the machineries to speed up other projects of the contractor. On 21st April 2016, the project site was mobilized for the second time to complete the remaining works together with other additional works agreed under, “Construction of K.Guraidhoo harbor Phase II” whose value is MVR12.7 million. Major design change was brought to the breakwater component of the project. This addendum addresses the modifications to the breakwater component. Length, shape and location of the breakwater in Phase II has been changed compared to the initial concept. New length of the break water is 340m compared to the 194m in the initial concept. Out of 340m, 62m will be constructed on south side of the harbour adjoining the Quay Wall. Under the current design, the breakwater will run over the natural channel on west of the main Quay Wall which will be reclaimed or filled to around -0.8m which is about 0.2m shallower than the existing depth of the shallow areas on both sides. Minor dredging is involved to source the fill material. Changes incorporated to the breakwater design is complimented by the island community. According to the initial harbour construction EIA, island community expressed dissatisfaction over the initial breakwater design as it did not cover the western side which is the predominant wave direction during the southwest monsoon. Proposed changes to the breakwater is a better alternative compared to the initial concept. It protects a larger area, specially the western side as mentioned earlier. The natural lagoon will be better enclosed to function more like a harbour, providing a safer habouring area. This design has also been identified in the 2014 EIA as an alternative. Environmental impacts of the proposed change were assessed for both construction and operation stage of the project. Most of the identified impacts are positive as they will improve the socio-economic situation of the island. As in all construction projects of this nature and explained in K.Guraidhoo harbour construction EIA, the main negative environmental impact of the project is identified to be the movement and settlement of sediment on the reef during the dredging to source the fill material for the channel. However, sedimentation due to the project is considered negligible as a volume required is less which is around 2000cbm. Additionally, the 62m breakwater on the southern side may enhance beach erosion as it will obstruct the longshore current around the island. But the effect of this breakwater on the shore might be difficult to identify as the area used to have Jetties previously. The most effective impact mitigation measure for the addendum would be to borrow sand from the first location proposed as the borrow area. This area is far from the reef, closer to the project area and once the work begins, will be enclosed by breakwater bed which will act as a bund wall in restricting and limiting the sediment flow. As outlined in 2014 harbour construction EIA, environment monitoring for sea water quality and shoreline changes should be carried out. Shoreline changes are to be monitored for a longer period of about 2 years after the project completion to identify any possible adverse effect due to the project. In an environmental and technical point of view, the proposed change to the breakwater of K.Guradhoo habour is justified and favoured by the island community.
URI: http://saruna.mnu.edu.mv/jspui/handle/123456789/5018
Appears in Collections:ތިމާވެށި
Environment A


Files in This Item:
File Description SizeFormat 
EIA First Addendum Report_K.Guraidhoo.pdf6.11 MBAdobe PDFView/Open


Items in Saruna are protected by copyright, with all rights reserved, unless otherwise indicated.