Title: | Environmental impact assessment for establishment of sewer network at Aa. Ukulhas |
Authors: | Wahhab, Mahfooz Abdul Adam, Ibrahim Rashihu |
Keywords: | Statutory requirements Ground conditions Water quality Noise Terrestrial vegetation Current measurement Benthic substrate anaylysis Fish census Geo-referencing Existing environment Climatic conditions Environmentally sensitive areas Groundwater Marine water quality Terrestrial vegetation Marine environment Island movement Hazard vulnerability Socio-economic status |
Issue Date: | Jan-2018 |
Citation: | Wahhab, M. A., & Adam, I. R. (2018). Environmental impact assessment for establishment of sewer network at Aa. Ukulhas. Male': Maldives |
Abstract: | The purpose of this EIA is to critically analyse and assess the potential environmental
impacts associated with the establishment of a sewer network in AA.Ukulhas and expose
the solutions and preferred alternatives as well as mitigation measures to minimize any
negative impacts whilst trying to derive the maximum positive impacts from the project; Existing sewer situation at the aforementioned island are not proper and are subject to cause
ground water contamination. In this sewer establishment project, sewer facilities are proposed to be constructed at a
location whereby public nuisance could be minimised along with little disturbance to the
natural setting of the proposed locations of sewer facility and allied pump stations for the
network. All the components of the sewer network will be constructed according to EPA
specification complying to both MEE and EPA regulations; Additionally, this study also involved identification of several alternative locations for
laying the outfall and selecting the most ideal location based on thorough study of the
current patterns, proximity to the public recreational beaches and ease of design
effectiveness. The preferred locations were selected based on best met design criteria of
EPA and environmental options; The construction works of sewer network presented in this report are not expected to
adversely impact the environment if the mitigation measures mentioned in the report are
followed. The most important mitigation measures are daily maintenance of machinery,
following chemical handling procedures, waste segregation and storage in closed labelled
containers until disposal to Thilafushi and most importantly following the EPA guidelines
for operation of sewer system; Potential groundwater contamination from damages to sewer network, potential impacts to
marine life from discharge of sewerage from the outfall, excavation and dewatering are the
most significant environmental impacts associated with the project. Therefore, it is
extremely important to follow the proposed mitigation measure, relevant guidelines and
regulations and the operation and maintenance manual of the sewer system during the
operational phase. Overall, the proposed project is expected to bring in positive outcomes. It is expected that
the newly established sewer network will ensure safe sanitation services to islandާ
community in addition to greatly reducing further disturbance and contamination of the
ground water and surrounding environment; and Monitoring is essential to ensure that environmental thresholds are not exceeded and mitigation measures proposed are working. Ground water and marine water quality
monitoring will be done according to the proposed monitoring schedule. |